Firelands Electric Cooperative moves forward with new all-in-one facility
NEW LONDON, March 21, 2018 — Firelands Electric Co-op held an official groundbreaking ceremony Oct. 30 for the construction of its new facility in New London. The cooperative selected Monroeville-based firm Janotta & Herner to construct the building, which is expected to be completed by the end of the year. The property will incorporate a community solar project that will be available as a generation resource to Firelands Electric’s membership.
Contractors completed some ground work before having to suspend construction in December. Weather conditions have not been favorable for work progress, but contractors are hopeful to resume construction over the next few weeks.
The U.S. Department of Agriculture (USDA) is investing $276 million in rural electric infrastructure to improve system efficiency and reliability throughout the United States. The type of loan guarantees being provided through USDA Rural Development’s Electric Program, the successor to the Rural Electrification Administration, invest capital in the form of low interest loans and loan-guarantees to nonprofit and cooperative associations, public bodies, and other utilities.
Firelands Electric is receiving $5.58 million in Rural Development loan funds to construct the cooperative’s new modern headquarters. The cooperative is among 14 recipients nationwide receiving loan funds for infrastructure improvement.
“Financing the project through the U.S. Department of Agriculture gives a lower fixed interest rate that will save our members money,” says General Manager Dan McNaull.
The cooperative’s board and management exercised due diligence by researching costs to maintain and repair the current three deteriorating facilities, versus building a new structure to meet the co-op’s needs. Having the cooperative’s facilities under one roof will offer improved communications and operating efficiencies, as well as provide a long-lasting structure to serve the co-op and its members for many years.
“The new building is an investment in both our future and in the community, which is reflective of the comprehensive strength and financial health of Firelands Electric Cooperative,” says McNaull. “Consolidation to a single facility will enhance communication, streamline member services and overall operations, and provide opportunities for improved efficiency.”
Janotta & Herner has provided a general timeline for the project. The tentative schedule is dependent on weather conditions.
- April/May – Start site work and grading; begin foundations, pour walls, and pre-engineer metal structure erection.
- June – Begin interior site prep: concrete floors, roof construction, electrical, plumbing, and HVAC radiant floor heating system.
- July – Finish the roof system prior to starting exterior walls and finishes.
- August – Complete wall and ceiling finishes; mechanical subcontractors finish electrical, plumbing, and HVAC systems within 30 days.
- September/October – Complete interior and exterior wall finishes, plumbing, and flooring; install fencing; excavating contractors finish grading work.
- November/December – Complete installation of the auto gates; pave concrete and asphalt areas; complete final finishes.
The cooperative ranks among the highest energy utilities in the country for customer satisfaction. Stay connected with the co-op through its Facebook page, facebook.com/FirelandsElectric, and Twitter feed, twitter.com/Firelands.